Water And Sewage Line Extension In Rothesay Proves Tough Going
Rock is slowing down the water and sewer line extension project on the Old Rothesay Road. Things got started on June 21st but at this point, crews are laying less than 20 feet of pipe daily because of what they are finding underground.
Crews have begun using explosives to crack the stones to get through the area near Hazen.
While that is going on, crews have also started installing pipe in the opposite direction starting at Colwell Lane and working toward Hazen.
The work is expected to finish up by December.