Things are back to normal at Point Lepreau and its once again at full power adding about 660 megawatts to the grid.
The station went offline last Saturday night after a problem with one of the turbine system pumps.
It was synchronized to the grid yesterday and over the last 24 hours power was gradually increased back to 100 per cent.
Site VP and Chief Nuclear Officer Sean Granville says they are pleased that their team of nuclear professionals to quickly identify and resolve the issues.