2009-04-24
13:26:36
The federal government has chosen Maricon Construction Management for a contract worth 17.6 million dollars to build a new wet lab at the St. Andrews Biological Station. The project will consolidate existing buildings into one state of the art wet lab facility. The building will house the majority of marine life and research operations.
Modernization of the St. Andrews Biological Station will also see the construction of a new 4,500 square metre science building with offices, laboratories, a computer centre, and a large library. Construction of the new wet lab is expected to begin this month and take about 65 weeks. All phases of the modernization project should be finished by June 2012.
No comments:
Post a Comment