NB Power releasing their latest update in the Point Lepreau refurbishment.
Technicians completing the polishing and inspection of 760 calandria tube sheet bores -- the next step is cleaning and taking the final measurements of each one which is slated to be competed by the end of the month.
Training on the installation of the tubes is also complete.
The tubes are scheduled to be installed in August with Lepreau set to go back online by the fall of next year.