Linked Header

Tuesday, April 13, 2010

Commissioning of Third Tank Underway










(Shot of LNG Site in Red Head)

              (File Photo)

Canaport LNG has begun the process of bringing it's third storage tank on-line.

This means flaring will happen and be visible from some vantage points within Saint John over the next two weeks.

There will also be a significant flare which is normal in the commissioning and cool down of each LNG storage tank.
Once the tank is ready, the flare will continue to operate at its standard height and will not be visible to most Saint John residents.